365telugu.com online news,Delhi,fevruary 7th,2022: Cleaning/ rejuvenation of rivers is an ongoing activity. It is the responsibility of the States/Union Territories (UTs), Local Bodies and Industrial Units to ensure required treatment of sewage and industrial effluents to the prescribed norms before discharging into river and other water bodies, coastal waters or land to prevent and control of pollution therein. For conservation of rivers, this Ministry has been supplementing efforts of the States/UTs by providing financial and technical assistance for abatement of pollution in identified stretches of rivers in the country through the Central Sector Scheme of Namami Gange for river Ganga and its tributaries and the Centrally Sponsored Scheme of National River Conservation Plan (NRCP) for rivers in other basins. Setting up of sewage treatment plant (STPs) is one of the important components of these programmes.

NRCP has so far covered polluted stretches on 34 rivers in 77 towns spread over 16 States in the country with a sanctioned cost of Rs.5961.75 crore, and inter-alia, a sewage treatment capacity of 2677 million litres per day (mld) has been created. Out of these, 3 projects have been sanctioned at a cost of Rs. 1164.33 crore for creation of 267 mld capacity STPs and sewerage network since 2019. Under the Namami Gange programme a total of 363 projects, including 160 projects for sewage treatment of 5023.98 mld and sewer network of 5227 kms, have been sanctioned at a cost of Rs.30841.53 crore. Out of these, 41 projects have been sanctioned at a cost of Rs. 6237.02 crore in 5 States under Namami Gange Programme that includes creation of 1421.74 mld capacity of STPs and sewerage network.  State/UT wise details of projects sanctioned under Namami Gange Programme and NRCP since 2019 and their status is enclosed at annexure.

In addition, under the Atal Mission for Rejuvenation and Urban Transformation (AMRUT) programme of Ministry of Housing & Urban Affairs, 889 sewerage & septage management projects amounting to Rs.34205 crore have been taken up, of which 400 projects amounting to Rs.9056 crore have been completed so far. Under the Swachh Bharat Mission (Urban) 2.0 launched in October, 2021, Rs.15883 crore has been allocated to States/UTs for waste water/used water management, including setting up of STPs and fecal sludge treatment plants (FSTP).

Proposals for pollution abatement works in the towns along polluted river stretches are received from the States/UTs from time to time for consideration under NRCP and sanctioned based on their prioritization, conformity with NRCP guidelines, availability of plan funds, etc.

This Information was given by the Minister of State for Jal Shakti, Shri Bishweswar Tudu in a written  reply in Rajya Sabha today.


State/UT wise details of sewerage infrastructure projects approved under Namami Gange Programme since 2019

Sr. No.TownName/ Nature of work STP Capacity to be created (in MLD)Date of approval (AAES)Approved project cost (INR in Cr.)Total expenditure incurred (INR in Cr.)Status as on December 31, 2021Original/ Tentative Date of Completion
Uttarakhand
1JoshimathInterception and Diversion (I&D)with STP3.78Original AA&ES 16.03.17 Revised AA&ES Date: 31.08.2162.4028.53Under ProgressMarch 2022
2Muni Ki RetiSludge ManagementPlant at Chorepani, Muni Ki Reti Uttarakhand State, under Namami Gange Programme 08.10.20208.674.01Under ProgressJanuary 2022
3Dehradun (Rispana & Bindal River)Interception & Diversion Works for Rispana & Bindal River in Dehradun (under Namami Gange Programme) 13.09.2018 Revised AA&ES 20.12.201963.7514.87Under ProgressMarch 2022
4Ramnagar (Kosi River)Interception & Diversion of Nallas Discharging in Kosi River at Ramnagar8.5015.02.2019 Revised AA&ES date 03.12.201955.0626.66CompletedCompleted on July 2021
5Srikot-Gangnali      (River Alaknanda)Pollution Abatement of River Alaknanda at Srikot-Gangnali Part A0.1308.03.20197.863.96CompletedCompleted on Feb 2021
6Udham Singh Nagar     (Dhela)(I&D) and STP work of 06 nos. Polluted River Stretches to Rejuvenate River Bhela, Dhela, Kichha, Kosi, Nandhore, Pilakhar and Kashipur Sewerage (I&D) Scheme (Dhela River)30.3017.09.2021199.36 AA&ES issued on 17.09.2021October 2023
Uttar Pradesh
1MirzapurInterception, Diversion and Treatment Works for abatement of Pollution of River Ganga at Mirzapur Town (under Hybrid annuity based PPP model-Namami Gange Programme)1828.05.2020129.080.02Under ProgressOctober 2023
2ChunarFaecal Sludge Management for pollution abatement at Chunar0.0107.03.20192.701.35Completed. (Under O&M)Completed on June 2021
3FarrukhabadInterception , Diversion & Sewage Treatment Works in Farrukhabad-Fategarh (under Hybrid annuity based PPP model-Namami Gange Programme)47.7016.10.2017 Revised AA&ES date 09.02.2021261.120Under ProgressApril 2024
4Faizabad(Saryu/Ghaghara River)Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District Ayodhya (Interception & Diversion with STP)3306.05.2021221.660Under ProgressMay 2024
5Sultanpur              (Gomti River)Interception & Diversion with STP at Sultanpur (Construction of New 7 mld & Upgradation of existing 5 mld to10 mld)1724.12.2018 Revised AA&ES 04.12.201970.1817.58Under ProgressMarch 2022
6Agra                    (Yaumna-River)Interception & Diversion with Rehabilitation of sewerage scheme at Agra(under Hybrid annuity based PPP model-Namami Gange Programme)177.6006.05.2020842.250Under Tendering. NIT published, (Bid under Evaluation)April 2024
7Muzaffarnagar (Hindon-River)Interception & Diversion works and STP at Muzaffarnagar(under Hybrid annuity based PPP model-Namami Gange Programme)54.5002.01.2019 Revised AA&ES 13.01.2020234.0328.37Under ProgressDecember 2022
8BudhanaInterception & Diversion works and STP at Budhana(under Hybrid annuity based PPP model-Namami Gange Programme)1018.02.201948.7610.46Under ProgressDecember 2022
9Bareilly                  (Ram Ganga-River)Interception & Diversion works and STP at Bareilly6303.01.2019271.390Under ProgressMarch 2024
10Jaunpur            (River Gomti)Interception & Diversion works and STP at Jaunpur3012.02.2019206.0592.04Under ProgressMarch 2022
11Meerut                     (River Kali)Pollution Abatement Works for River Kalikat Meerut under Meerut Municipality (Interception & Diversion with  STP )(under Hybrid annuity based PPP model-Namami Gange Programme)22006.05.2020690.710TenderingApril 2024
12Baghpat                    (River Yamuna)Interception & Diversion and STP works of Baghpat Town1419.02.201977.3618.48Under ProgressMay 2022
13Firozabad              (River Yamuna)Firozabad Sewerage Scheme (Interception & Diversion) works 01.03.201951.0821.43CompletedCompleted on July  2021.
14EtawahSewerage Scheme (Interception & Diversion) works44.9528.02.2019140.6038.66Under ProgressFebruary 2022
15Lucknow               (River Gomti)Interception & Diversion and STP works at Lucknow8202.03.2019 Revised AA&ES 06.05.2020213.910Under ProgressMarch 2024
16GhazipurSewerage,Sewage Treatment works at Ghazipur city(under Hybrid annuity based PPP model-Namami Gange Programme)2106.05.2020152.830Under ProgressOctober 2023
17KairanaInterception & Diversion works for Kairana Town, Distt- Shamli, Uttar Pradesh State under Namami Gange Programme1507.12.202078.421.39Under ProgressApril 2024
18BijnorFaecal Sludge Management               (Co-treatment) for abatement of pollution in River Ganga at Bijnor 14.12.20200.290Under ProgressMarch 2022 
19PratapgarhInterception & Diversion (I & D) of Drains and Sewerage Treatment Plant12.6303.11.202139.670AA&ES issued on 03.11.2021 
Bihar
1Patna-MokamaInterception, Diversion & Sewage Treatment Plant works under Namami Gange Programme828.07.2017 Revised Date 06.03.201960.9129.90Under ProgressFebruary 2022
2Maner-PatnaInterception & Diversion & Sewage Treatment Plant for Maner Town6.502.01.201941.361.49Under ProgressAugust 2022
3Danapur-PatnaInterception & Diversion & Sewage Treatment Plant for Danapur Town2508.02.2019103.27 Under ProgressSeptember 2022
4Phulwari shariff-PatnaInterception & Diversion & Sewage Treatment Plant for Phulwarishariff Town1308.02.201946.25 Under ProgressSeptember 2022
5BhagalpurInterception and Diversion and STP works in Bhagalpur (under Hybrid annuity based PPP mode-Namami Gange Programme)4512.10.2017 Revised AA&ES Date 10.11.2020413.290.07Under ProgressMarch 2024
6KahalgaonInterception and Diversion and STP scheme in Kahalgaon (under Namami Gange Programme)630.12.201925.770Tendering. NIT publishedOctober 2023
7BarahiyaInterception and Diversion and STP works in Barahiya (under Namami Gange Programme)630.12.2019270Tendering. NIT publishedMarch 2024
8Dehri (Sone)Interception and Diversion and STP works at Dehri (under Namami Gange Programme)2101.12.202163.89 AA&ES issued on 1.12.2021 
Jharkhand
1PhusroI & D and STP Project1515.12.202061.05 Under tenderingMay 2023
West Bengal
1Barrackpore MunicipalityDesign and Build of I & D structure. including Lock Gate and it’s all appurtenant structures as well as allied works at Barrackpore Municipality, North 24 Parganas, West Bengal State 08.10.20200.93 Under ProgressMarch 2022
2Maheshtala TownPollution Abatement works for River Ganga at Maheshtala- Municipal Town (Interception & Diversion with STP)under Hybrid Annuity based PPP mode3528.05.2020224.69 Under ProgressMarch 2024
3ChandanagarRejuvenation of existing STPs alongwith lifting stations & pumping station22.7008.03.201986.615.51Under ProgressJanuary 2022
Bansberia1
Uttarpara-Kortung-Konnagar225.96
Baidyabati64.80
Bhadreswar7.60
Serampore18.60 
Champdani1
4DurgapurInterception and Diversion Network for Drains including Pumping Stations and STP under Durgapur Municipality8003.01.2019287.53 Tendering (Revised DPR under Progress)April 2024
5Asansol & Kulti  (River Damodar & Barakar)Interception and Diversion Sewerage System & STP for Asansol & Kulti towns9512.02.2019384.96 Tendering (Revised DPR under Progress)April 2024
6NaihatiRejuvenation of existing STPs alongwith lifting stations & pumping stations18.0608.03.201965.5423.65Under ProgressApril 2022
Garulia4.10
Titagarh9.08
Panihati12
Khardah Municipality3
7North BarrackporePollution Abatement Works for River Ganga at North Barrackpore municipality(Interception and Diversion with STP)3802.12.2021214.78 Tendering 

State/UT wise details of projects approved under National River Conservation Plan since 2019  

Sr. No.TownName/ Nature of work Capacity (in mld)Date of approval (Administrative Approval &Expenditure Sanction)Approved project cost (in Cr.)Total expenditure incurred (in Cr.)StatusOriginal/ Revised Completion Date (M/D/Y)
State: Gujarat
1SuratPollution abatement and Conservation of river Tapi at 85 km stretch from Kakrapar Barrage to ONGC Bridge, Surat (Gujarat.)  Sewerage Network with STP, River Front Development, etc2505.3. 2019971.25198.84Under Progress (P)Original Completion Date: 3/31/2022 Revised Completion Date: 1/31/2024
State: Manipur
2.ImphalRejuvenation and Conservation of Nambul river at Imphal Sewerage Network with STP1719.01.201997.7242.22Under ProgressOriginal Completion Date: 1/31/2022 Revised Completion Date: 9/30/2022
State: Sikkim
3.GangtokUpgradation and Rehabilitation of sewers in Zone-I, Gangtok/ Extension and Rehabilitation of Sewer Line 28.10.202095.3619.50Under ProgressCompletion Date: 31/10/2023
 Total2671164.33260.56  